How to Set Your Electrician Labor Rate (Billable Hourly Rate)
The billable hourly rate is computed, not copied: burdened labor cost, plus overhead, plus planned profit, divided by the hours you can actually bill.
OEWS May 2025, SOC 47-2111 — a wage, not a bill rate
BLS median electrician wage
$30.38/hour
on wages up to $184,500 in 2026 (IRS)
Employer Social Security
6.2%
on all wages (IRS)
Employer Medicare
1.45%
6.0% on the first $7,000 of each employee's wages
FUTA after the max credit
0.6%
Your electrician labor rate has to sit above the BLS median electrician wage of $30.38/hour in May 2025, because a wage figure is a cost input, never a bill rate. There is no single number, and no benchmark table that settles it. Your billable rate is a computed figure: burdened labor cost, plus your share of overhead, plus planned profit, divided by the billable hours your crew can produce. This page walks that build-up line by line, then shows how to check the result against the market.
Start with burdened labor cost
The build-up starts on the cost side, with what one hour of your labor actually costs you, and the wage is only the first line of that stack.
BLS's OEWS survey put the median wage for electricians (SOC 47-2111, every license tier and segment counted together) at $30.38/hour nationally in May 2025, with the 25th percentile at $23.76 and the 75th at $40.36.
The spread is that wide, and the wage you post is the number the rest of the arithmetic loads onto.
On top of the wage sit the employer payroll taxes.
For 2026 the IRS sets the employer's FICA share at 6.2% Social Security on wages up to $184,500 and 1.45% Medicare on all wages.
One nearby figure is easy to misfile: the 0.9% Additional Medicare tax on an employee's wages over $200,000 is withheld from the employee.
It is not an employer cost to build into the rate.
FUTA adds 6.0% on the first $7,000 of each employee's wages; with the maximum 5.4% state credit the net rate is 0.6%.
Two more lines complete the burden.
Your state unemployment insurance charge is separate from FUTA and varies.
State rates were not collected in our research, so take yours from your state workforce agency.
Then add the insurance and benefits you provide, costed per paid hour, because they are funded out of the same revenue the rate brings in.
Wage + employer taxes + insurance + benefits is the burdened cost of one paid hour.
Until that stack is written down line by line, any hourly price on your quotes is a guess wearing a confident number.
And the crew behind the cost is its own subject: hiring electricians: the employer guide covers finding, screening and keeping the people whose hours you are pricing.
Add overhead
Burden covers the hour you bill.
Overhead covers the hours nobody bills for: truck payments and fuel, insurance renewals, shop or office rent, software and phones, bookkeeping, the licensing and bonding costs of operating, the estimator's salary on jobs you don't win, and the tools and test equipment on the shelves.
None of it appears on a job cost report as labor, and all of it has to be carried by the rate.
Two mechanisms move overhead into the price.
Divide total overhead for the year by the billable hours the company realistically produces, and you get an overhead amount attached to every billable hour.
Added to burdened cost, that sum is your break-even before profit.
Alternatively, load overhead as a multiplier on direct labor cost so that labor-heavy jobs automatically absorb more of it.
Either mechanism works; the failure mode is identical in both: overhead that is guessed rather than totaled from the books.
One caution before you trim this line by pushing costs onto the crew.
Tool cost in particular has a federal floor: the FLSA prohibits requiring employees to buy tools of the trade in any workweek where the cost cuts into required minimum or overtime wages.
Our research did not cover state deduction rules.
Confirm the current rules with the DOL Wage and Hour Division or employment counsel before you treat a tool charge as the employee's cost.
Billable vs paid hours
The division at the heart of the rate is billable hours, and they are not the hours you pay for.
Shop time, loading the truck, material runs, quotes and estimates that don't sell, training and safety meetings, windshield time between short calls: hours you pay for that carry no invoice of their own.
Every paid hour that produces no revenue raises the rate your charged hours must carry, because the same cost stack divides by fewer hours.
The paid side is wider than wrench time, too.
Under the FLSA, job-site-to-job-site travel during the day counts as hours worked, including travel from a required meeting place or after picking up tools at the shop.
An employee who drives, or is required to ride along as an assistant or helper, is working while riding; the exceptions the rule states are bona fide meal periods and sleep in employer-furnished facilities.
The hours that define your cost are therefore the hours on the clock, not the hours in front of a customer.
Confirm the treatment that applies to your crews with the DOL Wage and Hour Division or employment counsel.
That is why the honest billable figure comes out of your own time records rather than out of a rule of thumb: total the hours you paid last quarter, total the hours that hit invoices, and divide.
That ratio (your utilization, in your operation, this quarter) is the denominator for the whole build-up.
When it moves (a run of small service calls, a slow commercial month), the rate required to break even moves with it, which is worth knowing before you bid rather than after.
Profit margin
Profit is the third line in the rate, and the discipline is to plan it rather than hope for it.
A rate that recovers burden and overhead but treats profit as the leftover at year end has no line that funds the next truck, the next license renewal or the slow quarter.
It just hopes.
Be deliberate about the arithmetic convention.
Margin is profit as a share of the selling price; markup is profit added on top of cost.
The same profit described against the price and against the cost reads as two different percentages, which is how shops talk themselves into thinner pricing than they intended.
Pick one convention, use it in the rate build-up, in bids and in job-cost reports alike, and translate once for anyone who thinks in the other.
As for the target itself: our research found no primary-source industry net-profit-margin or markup figure for electrical contractors (the association surveys that collect one are member-only), so any ready-made margin or markup percentage deserves skepticism until you can see its source.
The right target comes out of your own structure: the risk you carry, how your customers pay, what your equipment and retention actually cost, and what the business needs to invest.
Decide it, divide it in, and let the rate, not wishful year-end arithmetic, produce it.
Checking the market
The computed rate needs an outside check, and the cleanest benchmark for the input side is the same BLS survey: OEWS May 2025 puts electricians (SOC 47-2111) at a $30.38/hour median nationally, with the 10th percentile at $20.50 and the 90th at $52.17, across 757,220 employed electricians.
BLS publishes the survey by state as well, so state-level figures exist for the states you staff.
Read those numbers for what they are: wages, meaning what employers across the industry pay employees.
They price the labor you hire, the first line of your cost stack.
They are not a bill rate.
A billable rate sits above the wage number by construction, because the same hour also carries employer taxes, insurance, the overhead share and profit.
Anyone comparing your rate to a wage figure (or to a competitor's advertised rate neither of you can see inside) is comparing different objects.
Two better outside checks.
First, your own books: what did last year's billable hours actually recover against burdened cost and overhead, job by job?
The underperforming job profiles show where the rate is already thin.
Second, the buyer's side of your market: what general contractors and commercial clients in your area accept.
On Davis-Bacon work (federal construction contracts in excess of $2,000), add the wage determination that covered contractors must pay at least, whether or not your formula does (see prevailing wage and certified payroll).
Posted pay on live listings is another window into what competitors pay for the same hours: current electrician jobs show the pay ranges employers advertise.
Raising rates
Rate reviews fail in two directions: never, or in a panic after a bad quarter.
The scheduled version is cheaper.
Put the inputs on a calendar — wage reviews, insurance renewals, and the tax parameters set for each calendar year (the Social Security wage base is $184,500 for 2026; FUTA applies to the first $7,000 of each employee's wages) — and recompute the build-up when they move, or at least once a year.
How to raise: quote new work at the new rate first, and give existing customers an effective date rather than a surprise on the next invoice.
Separate the labor-rate change from material pricing so the customer can see what actually moved, and hold already-quoted work to its quoted price unless the quote says otherwise.
If a customer leaves over a rate your own cost math supports, the account was priced below your costs.
That is information, however it stings.
The failure mode worth naming is absorbing cost increases in the margin line you just planned.
Every dollar of wage drift, insurance renewal or tax reset the rate doesn't recover comes straight out of profit, silently, on every billable hour.
The build-up makes that visible before the year-end numbers do: recompute, and if the rate must move, move it deliberately, with dates and in writing.
This page is employer information, not licensing, legal, accounting or tax advice. The payroll-tax parameters above are the IRS figures for 2026, and figures for later years can differ; travel-time and tool-cost rules are administered by the DOL Wage and Hour Division, and state rules can differ. Confirm current figures with the IRS, your state workforce agency and your accountant before you set the rate.
The rate build-up, in one list
- Start from the wage you actually pay for the role and the segment, not from a national median.
- Add employer payroll taxes: 6.2% Social Security on wages up to $184,500 (2026) and 1.45% Medicare on all wages.
- Add FUTA (6.0% on the first $7,000 of each employee's wages, 0.6% after the maximum 5.4% state credit) plus your state unemployment insurance rate.
- Add the insurance and benefits you fund, costed per paid hour.
- Total annual overhead from the books and divide it by the billable hours you realistically produce.
- Add planned profit: pick margin (share of price) or markup (added to cost) and stay in one convention.
- Divide the whole stack by billable hours, then check the result against your own job history and the buyer's side of your market.
Questions employers ask
Is my billable hourly rate the same as the wage I pay my electricians?
No. The wage is one input (BLS OEWS put the national median for electricians, SOC 47-2111, at $30.38/hour in May 2025), but the wage alone ignores employer payroll taxes, insurance and benefits, the share of overhead every billable hour must carry, and planned profit. The billable rate is burdened labor cost plus overhead plus profit, divided by billable hours, which is why it has to sit above the wage figures that feed it.
What does an employer pay on top of an electrician's wages?
For 2026, the IRS sets employer FICA at 6.2% Social Security on wages up to $184,500 and 1.45% Medicare on all wages. FUTA adds 6.0% on the first $7,000 of each employee's wages, or 0.6% after the maximum 5.4% state credit. State unemployment insurance is separate and varies; our research did not collect state rates, so get yours from your state workforce agency. Insurance and benefits you fund complete the burden.
What profit margin should an electrical contractor build into the hourly rate?
Build in a profit margin set from your own cost structure and risk, deliberately, rather than an industry figure. Our research found no primary-source industry margin or markup figure for electrical contractors (the association surveys that collect one are member-only), so treat any ready-made percentage with skepticism. Pick one convention, too: margin is profit as a share of price, markup is profit on top of cost, and the same profit reads as two different percentages.
Why is a competitor's hourly rate lower than mine?
A competitor's hourly rate can be lower because their wage mix, burden, overhead base and billable-hour denominator all differ from yours, and you cannot see inside their arithmetic. Some of their hours may be priced as a job rather than an hour, and an advertised rate is not necessarily the rate that reaches the invoice. Price from your own cost build-up and your own books, and let the market check inform the result, not replace it.